New paving update from Highway Superintendent Fisher: "I got a call from the Paving company today and paving will start August 6th on Van Wagner, August 9th on Myers and on the 9th & 10th Church St. Starting on the 11th, until finished, we'll be paving on River, Curry, Maple, Fuller, Beadart and Point Pl. I am sorry for the delay but it is out of my hands."
NOTICE TO RESIDENTS OF UPCOMING PAVING SCHEDULE
STARTING NEXT WEEK, THE BELOW LISTED ROADS ARE SCHEDULED TO BE PAVED AS FOLLOWS:
AUGUST 6th: Van Wagner Road AUGUST 9th: Myers Lane
AUGUST 9th & 10th: Church Street
AUGUST 11th until finished:
River Road, Curry Lane, Maple Lane, Fuller Lane, Point Place and Beadart Place
**NOTE** River Road, Curry Lane, & Fuller Lane are not wide enough and will have to be paved in one pass.
Please plan your trips accordingly.
The Town of Hyde Park Highway Department extends their appreciation for your cooperation and thanks you for your patience.